Skip to main content

Table 8 Balances and performances of the proposed grid-connected PV system in Kathmandu

From: Techno-economic feasibility analysis of a 3-kW PV system installation in Nepal

  Glob Hor kWh/m2 Diff Hor kWh/m2 T_Amb kWh Glob Inc kWh Glob Eff kWh E Arry kWh E_Grid kWh PR
January 138.2 25.98 8.90 208.1 204.9 618.5 597.9 0.871
February 140.7 32.69 13.34 186.9 184.0 544.0 525.5 0.852
March 169.2 58.43 18.84 193.7 189.5 550.0 531.3 0.831
April 183.7 66.20 23.70 185.5 180.7 513.3 495.8 0.810
May 191.3 77.28 25.06 175.7 170.5 489.4 472.2 0.814
June 175.2 88.42 24.25 155.9 151.1 441.6 426.0 0.828
July 156.4 82.90 23.41 140.5 135.9 401.7 386.9 0.835
August 157.5 78.17 23.27 140.5 135.9 401.7 386.9 0.835
September 138.3 70.56 22.40 146.0 141.9 414.4 399.8 0.830
October 148.9 55.05 20.34 182.0 178.5 518.6 500.9 0.834
November 131.0 31.37 15.55 187.9 184.8 541.8 523.7 0.844
December 139.0 19.92 11.06 221.5 218.3 648.0 626.4 0.857
Total 1869.2 686.98 19.20 2135.0 2086.9 6111.2 5901.1 0.838